Preface
Introduction
Definition
Principle of operation
Terminology
Better Air Flow
Pumping Head
Life Factor
Smaller Fan Motors
Casing
Classification
Thermal Design
Sump
Suction tank/auxiliary tank
Tower Structures
Fills
Sprinkler
Fan/ Fan Blades
Fan Drive Motor
Grills
Drift Eliminators
Installation
Towers
Sprinkler Assembly
Normal Conditions
Water quality Control
Post Erection Checks
Pre-commissioning checks
Maintenance Schedule
Pre-commissioning checks
•
Check level of sump, and fan ensure they are parallel to ground.
•
Check center pipe is vertical and sprinkler arms are all levelled, at right angles to center pipe.
•
Ensure no dirt/other foreign particles are present in sump, suction tank etc. Sweep clean/wash clean.
•
Rotate sprinkler with hand and ensure it is free.
•
Ensure fill top is even.
•
Ensure sprinkler arms are at a contrant level above the fills and that the arms do not rub against/ uneven fills, casing etc.
•
Ensure fan and motor assembly is free.
•
Check all bolts are tight and no loose parts noticed.
•
Fill water in sump and check and eliminate water leaks , if any.
•
Connect correct power (i.e 415V, 50Hz 3PH. AC ) supply to fan and check.
•
Direction of rotation of fan is correct and air is being sucked through screen above sump and discharged vertically upwards.
•
Vibrations are negligible.
•
Fan cable connection are made with lugs, and terminal cover gasket, is tight.
•
Establish water flow and check sprinkler rotates and check any unregulated by pass from sprinkler pipes.
About Us
|
Our Clients
|
Services
|
Products
|
Trouble Shooting
|
C-T Principles
|
Photo Gallery
|
Request For Quote
|
Contact Us
All Rights Reserved ©
Advance Cooling Towers Pvt. Ltd.
2006 - 2007.
Designed by:
Creative Web Mall